PH’s First Megawatt-Scale Floating Solar Plant Connects to Grid
2025-08-27 15:09
Favorite

Wedoany.com Report-Aug. 27, A 4.99 MW floating solar plant in Cebu City, Philippines, has been successfully connected to the grid. The project is situated at the Malubog Reservoir and has been developed with the involvement of Black & Veatch. Sungrow FPV also provided its floating solar system solutions, contributing to the technical execution of the facility.

The plant is designed to supply renewable energy directly to the Carmen Copper mining site. It is expected to cover about 10% of the mine’s overall electricity requirement, helping reduce dependence on conventional energy sources. By delivering power to industrial operations, the project demonstrates the growing role of renewable energy in supporting both local industry and broader sustainability objectives.

This floating solar installation also plays a part in the Philippines’ national clean energy development strategy. The government has set a target of achieving a 35% renewable energy share in the total power generation mix by 2030. By generating electricity from a non-land-based system, the plant also shows how renewable energy projects can make effective use of existing water resources while reducing land use pressures.

Black & Veatch emphasized that the completion of the Malubog Reservoir project highlights its continued work in providing innovative power solutions across the region. Sungrow FPV’s floating solar technology was integrated to ensure stability and efficiency in the reservoir environment, further strengthening the project’s operational reliability.

The connection of this facility to the national grid underlines the importance of diversifying renewable energy development methods. Floating solar has emerged as a practical option in countries where available land may be limited, while at the same time offering cooling benefits that improve system performance.

As the Philippines moves forward with its renewable energy transition, projects like the Malubog Reservoir solar plant provide both immediate and long-term benefits. They reduce carbon emissions, create pathways for sustainable mining operations, and contribute to meeting national targets. The project also reflects how collaboration between international technology providers and local industries can accelerate progress in the clean energy sector.

The successful commissioning of the 4.99 MW floating solar facility demonstrates the viability of renewable energy integration in diverse environments. Its role in supplying a significant portion of the Carmen Copper mine’s energy needs and contributing to the Philippines’ 2030 renewable energy share target highlights the broader impact of such projects on energy security and environmental sustainability.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com